published Friday, January 27th, 2012

Inspectors cite inadequate work planning at Browns Ferry Nuclear Plant

The containment door of the Unit 2 reactor, opened for maintenance is 7 feet thick of reinforced concrete.  Photo by Michael Mercier/ The Huntsville Times
The containment door of the Unit 2 reactor, opened for maintenance is 7 feet thick of reinforced concrete. Photo by Michael Mercier/ The Huntsville Times
Follow us on Twitter for the latest breaking news

ATHENS, Ala. — Members of the Nuclear Regulatory Commission’s inspection team for the Browns Ferry “red” safety finding ticked off a litany of TVA deficiencies Thursday during a public meeting at the plant.

The team, designed to get Browns Ferry back on track after the Athens, Ala., plant received the NRC’s highest safety concern flag last year, pulled no punches.

“We did identify safety culture problems, both with the workforce and with management,” said John Jandovitz, the team leader for the second group of on-ground inspectors who spent weeks watching maintenance and other work at the plant.

“Work planning is weak, and people here told us, ‘Yeah, we know. We just live with it.’ That’s not appropriate,” Jandovitz said.

“Enforcement procedures weren’t getting done, and it was tolerated by management,” he added. “We saw work removed from the schedule and no one ever questioned it.”

Jandovitz said that as inspectors kept returning and their scrutiny continued, they saw managers and other workers begin to question schedule and work changes.

“We thought a new program had been introduced, but we learned it wasn’t new. A program had been there all along. It just hadn’t been enforced,” he said.

Browns Ferry Nuclear Plant Manager Keith Polson and TVA Chief Nuclear Officer and Vice President Preston Swafford took the medicine with somber faces in front of a packed conference room at the Browns Ferry Training Center.

“Our goal is to strive for excellence,” Polson said. “We get it. And we agree with what was said here today. Our goal is to be the best nuclear plant in the country.”

Swafford said TVA and the whole TVA nuclear fleet is learning “a great deal as we dig in” with the red finding inspections and with TVA’s own corrective action program.

“Some of these things have been deficient for some time. Our [corrective action] program is strong but it takes time,” Swafford said. “It’s an ugly period as we identify the issues, but you can’t get well until you get the issues up on top of the table and start fixing them.”

Joseph Smith, a resident of the Blue Water Creek community near Athens, told NRC and TVA that someone “needs to be held accountable and fired” because the plant is “not being operated in a way that protects me.”

“I’m afraid. And my neighbors and friends are afraid of this plant. It hasn’t blown up and killed us all, and I thank you for that. But you can do better,” Smith said.

about Pam Sohn...

Pam Sohn has been reporting or editing Chattanooga news for 25 years. A Walden’s Ridge native, she began her journalism career with a 10-year stint at the Anniston (Ala.) Star. She came to the Chattanooga Times Free Press in 1999 after working at the Chattanooga Times for 14 years. She has been a city editor, Sunday editor, wire editor, projects team leader and assistant lifestyle editor. As a reporter, she also has covered the police, ...

related articles »

May 23rd, 2012

The Nuclear Regulatory Commission has extended the time for TVA to meet a new fire protection requirement at Browns Ferry ...

Sept. 28th, 2011

Nuclear regulators have called a public meeting Monday with TVA at Browns Ferry Nuclear Plant to discuss the results of ...

Aug. 31st, 2011

TVA may have to spend more than $10 million for an intensive set of nuclear regulatory inspections at the utility's ...

Aug. 18th, 2011

On the eve of a TVA board meeting and an expected vote on restarting construction at Bellefonte Nuclear Plant, the ...

videos »         

photos »         

e-edition »

advertisement
advertisement
400 East 11th St., Chattanooga, TN 37403
General Information (423) 756-6900
Copyright, permissions and privacy policy, Ethics policy - Copyright ©2012, Chattanooga Publishing Company, Inc. All rights reserved.
This document may not be reprinted without the express written permission of Chattanooga Publishing Company, Inc.